India's national highways and the NHAI model
India's national highway network reached about 1,46,572 km in FY 2025-26, up from about 91,287 km in 2014, but construction has slowed from a peak of about 37 km/day in FY21 to about 29 km/day in FY25, and the ministry acknowledged in July 2026 that delays run across states. The 2026-27 Budget gives the ministry Rs 3.10 lakh crore, with NHAI barred from market borrowing since 2022-23 and its debt down to about Rs 2.4 lakh crore; the gap is filled by recycling built roads through Toll-Operate-Transfer and InvITs, and since mid-2026 by a revived private BOT model. On tolling, the ministry has deferred GPS-based charging and is rolling out barrier-less Multi-Lane Free Flow on FASTag and number-plate cameras, while the FASTag Annual Pass passed one crore issuances in September 2026.
Ministry of Road Transport and HighwaysMinistry of Finance
The scale of the build-out
India’s national highway network stood at about 1,46,572 km in FY 2025-26, up from about 91,287 km in 2014 — an increase of about 61% on the ministry’s own figures (PIB). National highways are a small fraction of India’s total road length but carry a disproportionate share of freight and long-distance traffic, which is why the Ministry of Road Transport and Highways holds one of the largest single allocations in the Union Budget: Rs 3,09,875 crore for 2026-27, 8% above the 2025-26 revised estimate, of which Rs 1,87,293 crore (60%) goes to NHAI (PRS).
The pace of construction has cooled. The ministry told the Rajya Sabha that it fell to about 29 km/day in FY25 (10,660 km) from 34 km/day in FY24, against a peak of about 37 km/day in FY21 (Business Standard). For FY26, NHAI alone built 5,313 km, above its 4,640-km target but below its 5,614 km of FY25 (IBEF), and CareEdge Ratings put the overall pace near 27 km/day (The Tribune). Of the 10,389 km of access-controlled high-speed corridors and greenfield expressways awarded, 4,809 km were complete and 5,580 km under construction as of July 2026 (PIB). Under Bharatmala Phase I, 26,425 km had been awarded and 22,590 km built by March 2026 (PIB).
Delay is officially acknowledged. Answering the Lok Sabha on 23 July 2026, the ministry listed state-wise projects awarded in the previous five years that had overrun their completion schedules — Maharashtra, Uttar Pradesh, Andhra Pradesh and Karnataka had the most — named land acquisition, statutory clearances, utility shifting, encroachment and contractor performance as the causes, and reported delay penalties of about Rs 2,732 crore over three years, of which Rs 780 crore had been recovered (Lok Sabha USQ 843). On 30 September 2026 NHAI ordered special quality inspections of 17 large projects won at more than 15% below estimated cost (PIB).
The NHAI delivery model
NHAI, the statutory body operational since 1995, develops and finances most of the network. It awards highways under three principal modes: Engineering-Procurement-Construction (EPC), where the government funds the work; Build-Operate-Transfer (BOT), where a private concessionaire finances construction and recovers it through tolls; and the Hybrid Annuity Model (HAM), which splits capital between the government and the developer. The mix decides how much risk sits with the state: on PRS’s reading of budget data, the private share of road construction fell from 51% in 2014-15 to about 15% in 2023-24 (PRS).
In 2026 the ministry moved to bring private capital back into BOT. The Cabinet approved the 117.7 km Kanpur–Kabrai corridor on BOT (Toll) terms on 1 July 2026 (PIB), and in August the ministry told the Rajya Sabha that the BOT bidding and concession documents had been amended to let fund houses bid on financial strength, add compensation for Annual Pass revenue losses, pay termination compensation before commercial operation once progress passes 20%, and replace dispute resolution boards with arbitration (below Rs 10 crore) or conciliation and mediation (PIB).
Bharatmala Phase I, approved in 2017 for about 34,800 km at about Rs 5.35 lakh crore, is the programme behind much of the recent network. The CAG’s 2023 audit flagged a sanctioned civil cost of about Rs 23.89 crore per km against the approved Rs 13.98 crore, along with scope changes (CAG; PRS).
Asset recycling and the debt it services
The defining feature of the NHAI model is asset recycling — selling the future toll rights of completed highways and channelling the proceeds into construction and debt repayment. NHAI’s market borrowing has been halted since 2022-23; its outstanding debt peaked at Rs 3.48 lakh crore in 2021-22 and stood at Rs 2,39,818 crore in November 2025 (PRS).
Two channels carry the recycling. Under Toll-Operate-Transfer NHAI auctions operational stretches for a lump sum over a fixed concession; ToT Bundle-19, the first deal of FY27, went to an Edelweiss-backed platform for Rs 2,259 crore (Construction World). The second is the InvIT: the privately placed National Highways Infra Trust and, since its listing on 24 March 2026 after an issue oversubscribed about 14 times, the public Raajmarg Infra Investment Trust (PIB). NHAI realised about Rs 28,307 crore in FY26 (Business Standard) and has listed 17 assets of about 1,692.5 km for FY27, separate from the assets earmarked for the public InvIT (Swarajya).
Tolling: the Annual Pass and barrier-less MLFF
The FASTag Annual Pass, launched on 15 August 2025 for private cars, jeeps and vans, gives one year or 200 plaza crossings for a one-time fee — Rs 3,075 in 2026-27. By June 2026 more than 77 lakh passes had been issued and they accounted for about 33% of car electronic-toll transactions (PIB); on 28 September 2026 NHAI reported more than one crore passes issued (PIB). CRISIL Ratings had estimated in 2025 that the pass could lower toll operators’ revenues by 4-8% — an attributed ratings estimate, not a ministry figure (Business Standard); the amended BOT documents now provide compensation for that loss.
The technology route for barrier-free tolling has been settled for now. In July 2026 the ministry told Parliament that an apex committee and a high-level empowered committee had recommended further deliberation on GPS-based tolling on security and privacy grounds, and that it would instead implement Multi-Lane Free Flow (MLFF) on existing FASTag RFID plus automatic number-plate recognition — awarded at 17 plazas, live at five, with bids invited for 104 more (PIB). The first MLFF plaza opened at Chorayasi on NH-48 in Gujarat on 1 May 2026 (PIB); more than 98% of national highway toll is already collected through FASTag.
Planning across modes
On 6 October 2026 the Cabinet approved an Integrated Transport & Logistics Authority to prepare a National Transport Master Plan spanning roads, rail, ports, aviation and waterways, check each transport ministry’s plans against it, technically appraise and monitor central projects of Rs 500 crore or more, and build a transport data repository drawing on FASTag, Vahan and e-way bill data (PIB). Financial appraisal stays with the existing mechanisms.
What is contested
The core numbers — network length, kilometres built, budget, debt — come from ministry statements, budget documents and parliamentary replies and are broadly consistent. What is contested is interpretation: whether the slower pace reflects a maturing network with harder stretches or execution, land and financing bottlenecks the ministry itself now lists; whether recycling built roads is a durable financing model or a front-loading of future toll revenue; whether the revived BOT model draws private capital back after its share fell to about 15%; and how far the Annual Pass dents the toll base. This brief characterises those positions and attributes them; it does not adjudicate or project outcomes.
Who owns this topic (and why we’re here)
Search results for India’s highways and the NHAI model are dominated by UPSC and exam-prep explainers — Drishti IAS, Vajiram & Ravi, Testbook, BYJU’S, Legacy IAS — which list the NHAI Act, Bharatmala components and contracting models but freeze at the last syllabus revision, and by trade coverage of individual ToT or InvIT rounds. IndiaStand’s advantage is structural: a maintained dossier on the institution plus this living brief, which ties the build-out, the EPC/BOT/HAM mix, asset recycling, NHAI’s debt and the tolling shift into one attributed, dated state of play — updated as the numbers move.
Maintained topic brief. Analysis by IndiaStand — it characterises the state of play and the range of positions actually held, attributes each claim, and makes no forecast and no recommendation.
Sources
- PRS — Demand for Grants 2026-27 Analysis, Road Transport and Highways · India
- PIB — Highways Transformation: network and Bharatmala status (14 Jun 2026) · India
- PIB — Construction of national high-speed corridors and greenfield expressways (Rajya Sabha, 22 Jul 2026) · India
- Lok Sabha Unstarred Question 843 — National Highway projects (23 Jul 2026) · India
- PIB — FASTag-based toll collection and digital tolling system (Rajya Sabha, 22 Jul 2026) · India
- PIB — Highway infrastructure financing and investment: BOT model concession amendments (12 Aug 2026) · India
- PIB — Cabinet approves Kanpur–Kabrai section of NH-34 on BOT (Toll) mode (1 Jul 2026) · India
- PIB — FASTag Annual Pass reaches one crore milestone (28 Sep 2026) · India
- PIB — India's first Multi-Lane Free Flow tolling system launched in Gujarat (1 May 2026) · India
- PIB — NHAI special quality checks on projects with abnormally low bids (30 Sep 2026) · India
- PIB — Cabinet approves Integrated Transport & Logistics Authority (6 Oct 2026) · India
- Business Standard — NH construction pace slows to 29 km/day in FY25 (Rajya Sabha reply) · India
- The Tribune — NH construction slows to 27 km/day in FY26 from 37 km/day in FY21 (CareEdge Ratings) · India
- IBEF — NHAI constructs 5,313 km of national highways in FY26 · India
- PRS — Implementation of Phase 1 of Bharatmala Pariyojana · India
- CAG — Report No. 19 of 2023, Implementation of Phase-I of Bharatmala Pariyojana · India
- Business Standard — NHAI monetises Rs 28,307 crore highways in FY26, nears target · India
- Construction World — Edelweiss platform secures NHAI ToT Bundle 19 for Rs 22.59 bn · India
- Swarajya — NHAI shortlists 17 highway projects for FY27 monetisation · India
- PIB — Raajmarg Infra Investment Trust to list on BSE (23 Mar 2026) · India
- Business Standard — FASTag annual pass may cut toll operators' revenues 4-8% (CRISIL) · India
For organisations
Need this for a decision your organisation is making?
- Commission a reviewed evidence pack → This evidence, re-checked against your own criteria and states, reviewed and delivered with a source register and an unknowns log.
- Monitor these institutions → We re-check the sources behind the claims you depend on and brief you when one materially changes.
- Submit your research question → Tell us the decision it supports and the deadline; we scope it before quoting.
We establish what is documented, what changed, who is responsible, where evidence conflicts and what remains unknown. We do not give investment, legal or policy advice — the decision stays with you or your adviser. Services · Methodology