Implementation tracker · projects · 12 units
India Semiconductor Mission units: from approval to operation
As of 7 October 2026, 12 manufacturing units have been approved under the Semicon India Programme (Semicon 1.0), across Gujarat, Assam, UP, Andhra Pradesh, Punjab, Odisha. 5 are documented as in commercial operation — Micron, CG Semi, Kaynes Semicon, CDIL discrete semiconductor expansion, Suchi Semicon — all assembly, packaging or discrete-device units. The only silicon fab, Tata–PSMC at Dholera, is under construction. Official releases differ on the operating count (three or five); each unit's stages below are separately sourced.
Scope. Units approved by the Union Cabinet under Semicon 1.0, and the project stages documented for each: approved, land allotted, construction started, pilot output, commercial operation. An inauguration is recorded as commercial operation only where the official release says production began; no source quantifies volumes shipped. Units under other schemes (such as SPECS) are excluded.
Updated · Sources checked 2026-10-07 — no material change found
At a glance: furthest documented stage
Each date is a separately sourced claim; "—" means not evidenced, not "did not happen". Approval is the first stage documented for every unit.
| Unit | Approved | Construction started | Pilot output | Commercial operation |
|---|---|---|---|---|
| Micron ATMP plant, SanandGujarat | 2023-06 Verified | 2023-09 Verified | — | 2026-02-28 Verified |
| CG Semi OSAT plant, SanandGujarat | 2024-02-29 Verified | 2024-03-13 Verified | 2025-08-28 Verified | 2026-07-04 Verified |
| Tata semiconductor assembly and test plant, Jagiroad (Assam)Assam | 2024-02-29 Verified | 2024-03-13 Verified | 2026-10-03 Reported | — |
| Tata Electronics–PSMC semiconductor fab, DholeraGujarat | 2024-02-29 Verified | 2024-03-13 Verified | — | — |
| Kaynes Semicon OSAT plant, SanandGujarat | 2024-09-02 Verified | — | 2025-04 Reported | 2026-03-31 Verified |
| HCL–Foxconn semiconductor unit, Jewar (Uttar Pradesh)UP | 2025-05-14 Verified | 2026-02-21 Verified | — | — |
| ASIP OSAT unit, VisakhapatnamAndhra Pradesh | 2025-08-12 Verified | 2026-08-01 Verified | — | — |
| CDIL discrete semiconductor expansion, MohaliPunjab | 2025-08-12 Verified | — | — | 2026-09-17 Verified |
| 3D Glass Solutions advanced packaging unit, BhubaneswarOdisha | 2025-08-12 Verified | 2026-04-19 Verified | — | — |
| SiCSem silicon carbide fab, BhubaneswarOdisha | 2025-08-12 Verified | 2025-11-01 Verified | — | — |
| Crystal Matrix GaN Micro-LED unit, DholeraGujarat | 2026-05-05 Verified | — | — | — |
| Suchi Semicon OSAT plant, SuratGujarat | 2026-05-05 Verified | — | — | 2026-09-17 Verified |
Gujarat · furthest documented: Commercial operation
Micron ATMP plant, Sanand
As of 7 October 2026, Micron's Rs 22,516 crore assembly, testing, marking and packaging (ATMP) plant at Sanand, Gujarat — the first unit approved under the Semicon India Programme, in June 2023 — is in commercial operation. The Prime Minister inaugurated it on 28 February 2026, in what PIB described as the commencement of commercial production, making it the first ISM-approved unit to reach that stage. Production volumes are not documented.
-
Union Cabinet approves Micron ATMP proposal, Rs 22,516 crore, 50% central fiscal support pari-passu.
Only month stated in official sources read.
-
Groundbreaking at Sanand within three months of approval.
Day (2023-09-23 bhoomi pujan) reported by ANI/Business Today; not read directly. Milestone/disbursement agreements signed 2023-12-06.
-
Prime Minister inaugurates the Sanand ATMP, described as commencement of commercial production.
Inauguration plus company statement; volumes produced not quantified in sources.
- Unknown: What volumes is the plant producing? — Not quantified in the sources read.
Gujarat · furthest documented: Commercial operation
CG Semi OSAT plant, Sanand
As of 7 October 2026, CG Semi's Rs 7,584 crore outsourced assembly and test (OSAT) plant at Sanand, Gujarat — a CG Power, Renesas and Stars Microelectronics venture approved on 29 February 2024 — is in commercial operation. Its pilot line was inaugurated on 28 August 2025 and the plant on 4 July 2026, when PIB cited commencement of commercial chip packaging.
-
Cabinet approves CG Power-Renesas-Stars OSAT at Sanand, Rs 7,600 crore, 15 million chips/day.
-
Prime Minister lays foundation stone for the Sanand OSAT.
-
Union IT Minister and Gujarat CM inaugurate the OSAT pilot line; chips for customer qualification.
-
Prime Minister inaugurates the CG Semi OSAT; release cites commencement of commercial chip packaging.
Release cites 20 crore units/year now; actual shipped volumes not documented.
- Unknown: What volumes are being shipped? — PIB cites a stated capacity; shipped volumes are not documented.
Assam · furthest documented: Pilot output
Tata semiconductor assembly and test plant, Jagiroad (Assam)
As of 7 October 2026, Tata Semiconductor Assembly and Test's Rs 27,120 crore ATMP unit at Jagiroad, Morigaon district, Assam, has been approved (29 February 2024) and is under construction (foundation stone 13 March 2024). On 3 October 2026 the Assam Chief Minister said the first clean room was ready and pilot chip production had begun; that statement has not been confirmed by PIB or ISM and is recorded as reported, single-origin. No commercial production is documented.
-
Cabinet approves TSAT ATMP at Morigaon (Jagiroad), Assam; Rs 27,000 crore at approval, 48 million chips/day.
-
Prime Minister lays foundation stone for the Morigaon OSAT.
-
Assam Chief Minister says first clean room is ready and pilot chip production has begun.
Both articles relay one statement by the Assam CM (single origin). Not confirmed by PIB/ISM. Second clean room under construction; no commercial production documented.
- Unknown: Has pilot production been confirmed by ISM or the company? — Only the Assam Chief Minister's statement, relayed by news, was found.
Gujarat · furthest documented: Construction started
Tata Electronics–PSMC semiconductor fab, Dholera
As of 7 October 2026, Tata Electronics' silicon fab at Dholera, Gujarat — built with Taiwan's Powerchip Semiconductor Manufacturing Corp, 50,000 wafer starts per month, Rs 91,526 crore — is India's only approved silicon fab. It was approved on 29 February 2024, its foundation stone was laid on 13 March 2024, and a Fiscal Support Agreement was signed on 5 March 2025. No pilot or commercial output is documented; the Semicon 2.0 release states the first fab is scheduled to be commissioned in 2028.
-
Cabinet approves 50,000 WSPM fab at Dholera with PSMC; Rs 91,000 crore stated at approval (Rs 91,526 crore in later releases).
-
Prime Minister lays foundation stone (virtually) for the Dholera fab.
- Unknown: Has any tool installation, pilot wafer or production been documented? — Not in the official sources read; the Tata Electronics CEO said on 17 September 2026 that construction is on track.
Gujarat · furthest documented: Commercial operation
Kaynes Semicon OSAT plant, Sanand
As of 7 October 2026, Kaynes Semicon's Rs 3,307 crore OSAT plant at Sanand, Gujarat — approved on 2 September 2024 — is in commercial operation following its inauguration on 31 March 2026. Pilot-line manufacturing from April 2025 is reported in news only.
-
Cabinet approves Kaynes Semicon unit at Sanand, Rs 3,300 crore, 60 lakh chips/day.
-
Manufacturing on pilot line reported to have begun in April 2025; first module shipment (about 900 IPMs) to a US firm reported 2025-10-16.
News only; not confirmed in PIB/ISM sources read.
-
Prime Minister inaugurates the Kaynes plant, marking commencement of production.
- Unknown: When did construction start? — No construction-start date was found.
UP · furthest documented: Construction started
HCL–Foxconn semiconductor unit, Jewar (Uttar Pradesh)
As of 7 October 2026, the HCL–Foxconn joint venture's Rs 3,706 crore OSAT unit near Jewar airport in the Yamuna Expressway Industrial Development Authority area, Uttar Pradesh — for display driver chips — has been approved (14 May 2025) and had its foundation stone laid on 21 February 2026. No pilot or commercial output is documented.
-
Cabinet approves HCL-Foxconn JV unit near Jewar airport (YEIDA): display driver chips, 20,000 wafers/month, Rs 3,700 crore.
-
Prime Minister virtually lays foundation stone (groundbreaking) of India Chip Pvt Ltd at YEIDA.
PIB item is the advance notice (2026-02-20); occurrence confirmed by All India Radio (newsonair.gov.in) report on the day.
- Unknown: When was land allotted? — No land-allotment date was found.
Andhra Pradesh · furthest documented: Construction started
ASIP OSAT unit, Visakhapatnam
As of 7 October 2026, Advanced System in Package Technologies' OSAT unit in Andhra Pradesh — approved on 12 August 2025 with Rs 480 crore approved investment and a technology tie-up with South Korea's APACT — had its foundation stone laid at Tarluvada, Visakhapatnam on 1 August 2026, per two news reports; no PIB release on the groundbreaking was found.
-
Cabinet approves ASIP unit in Andhra Pradesh, 96 million units/year, with APACT technology tie-up.
-
Prime Minister virtually lays foundation stone at Tarluvada, Visakhapatnam, with AP CM.
Two news origins; no PIB release found. News cites Rs 2,500 crore total plan vs Rs 480 crore approved (pib:2247814).
- Conflict: Investment: Rs 480 crore approved per a Lok Sabha reply (PIB 2247814) versus a Rs 2,500 crore total plan cited in news at the groundbreaking.
Punjab · furthest documented: Commercial operation
CDIL discrete semiconductor expansion, Mohali
As of 7 October 2026, Continental Device India's brownfield expansion of its discrete semiconductor facility at Mohali, Punjab (MOSFETs and IGBTs in silicon and silicon carbide) — approved on 12 August 2025 — has commercial production lines inaugurated on 17 September 2026.
-
Cabinet approves brownfield expansion of discrete semiconductor facility at Mohali (MOSFETs, IGBTs; Si and SiC).
-
Prime Minister virtually inaugurates commercial production lines at CDIL, Mohali.
Inauguration of lines; volumes not documented. pib:2313324 (2026-09-22) still states three facilities in commercial production.
Odisha · furthest documented: Construction started
3D Glass Solutions advanced packaging unit, Bhubaneswar
As of 7 October 2026, 3D Glass Solutions' advanced packaging and embedded glass-substrate unit at Info Valley, Bhubaneswar — approved on 12 August 2025, total investment Rs 1,943.53 crore including Rs 799 crore of central support — is under construction following its foundation stone on 19 April 2026.
-
Cabinet approves vertically integrated advanced packaging and embedded glass substrate unit at Info Valley, Bhubaneswar.
-
Foundation stone laid at Info Valley, Bhubaneswar; total investment Rs 1,943.53 crore incl. Rs 799 crore central support.
Odisha · furthest documented: Construction started
SiCSem silicon carbide fab, Bhubaneswar
As of 7 October 2026, SiCSem's Rs 2,066 crore integrated silicon carbide compound-semiconductor fab and packaging unit at Info Valley, Bhubaneswar — approved on 12 August 2025 — is under construction, with groundbreaking on 1 November 2025 reported by two independent news outlets. No output is documented.
-
Cabinet approves integrated SiC compound semiconductor fab + packaging at Info Valley, Bhubaneswar - first commercial compound fab.
-
Bhoomi pujan/groundbreaking of SiCSem facility at Info Valley, Bhubaneswar, attended by Odisha CM.
Two independent news origins; not in PIB/ISM sources read. A virtual foundation stone was reportedly laid 2025-01-31, before ISM approval.
Gujarat · furthest documented: Approved
Crystal Matrix GaN Micro-LED unit, Dholera
As of 7 October 2026, Crystal Matrix's integrated compound-semiconductor fab and ATMP unit at Dholera, Gujarat, for gallium nitride Mini/Micro-LED display modules and GaN foundry services, has been approved (5 May 2026). No groundbreaking is documented. PIB gives only a two-unit investment total (about Rs 3,936 crore with Suchi Semicon); the Rs 3,068 crore figure is from news.
-
Cabinet approves integrated compound semiconductor fab + ATMP at Dholera for GaN Mini/Micro-LED display modules and GaN foundry services.
- Conflict: Classification: compound semiconductor fab plus ATMP at approval (PIB 2258119) versus 'GaN Micro LED Display Fab' (PIB 2284796).
Gujarat · furthest documented: Commercial operation
Suchi Semicon OSAT plant, Surat
As of 7 October 2026, Suchi Semicon's OSAT unit at Surat, Gujarat, for discrete semiconductors — approved on 5 May 2026 — has commercial production lines inaugurated on 17 September 2026. News reports that its Surat facility was already functional before ISM approval; the ISM-approved scope is lead-frame and wire-bond packaging.
-
Cabinet approves Suchi Semicon OSAT at Surat for discrete semiconductors, 1033.20 million chips/year.
-
Prime Minister virtually inaugurates commercial production lines at Suchi Semicon, Surat.
News (2026-05-05) says its Surat OSAT was already functional before approval; ISM-approved scope is lead-frame/wirebond packaging.
Questions this page answers
- Is Micron's Sanand ATMP plant operational?
- Yes. It was inaugurated on 28 February 2026, which PIB described as the commencement of commercial production — the first ISM-approved unit to reach that stage. Volumes are not documented.
- What stage has the Tata semiconductor assembly and test plant at Jagiroad, Assam reached?
- Officially documented: approved (29 February 2024) and under construction (foundation stone 13 March 2024). Pilot production was reported on 3 October 2026 on the Assam Chief Minister's statement, not yet confirmed by PIB or ISM. No commercial production is documented.
- What is the documented status of the Tata–PSMC semiconductor fab at Dholera?
- As of 7 October 2026: approved (29 February 2024), foundation stone laid (13 March 2024), Fiscal Support Agreement signed (5 March 2025), construction described as on track by the company on 17 September 2026. No pilot or commercial output is documented; the government's Semicon 2.0 release states commissioning is scheduled for 2028.
- What is documented about the HCL–Foxconn semiconductor unit near Jewar, Uttar Pradesh?
- Approved by the Union Cabinet on 14 May 2025 (Rs 3,700 crore at approval; display driver chips) and foundation stone laid on 21 February 2026. No production is documented as of 7 October 2026.
Source register
- Micron's semiconductor project at Sanand in Gujarat on fast track · official · published 2023-12-06 · origin pib:1983128
- Prime Minister Shri Narendra Modi inaugurates Micron Technology's Semiconductor Assembly, Test and Packaging (ATMP) facility in Sanand, Gujarat · official · published 2026-02-28 · origin pib:2233998
- Prime Minister Shri Narendra Modi Inaugurates SEMICON India 2026; Unveils India's Ambitious Roadmap for Transition to Semicon 2.0 · official · published 2026-09-17 · origin pib:2311726
- Giant leap for India Semiconductor Mission: Cabinet approves three more semiconductor units · official · published 2024-02-29 · origin pib:2010132
- PM participates in 'India's Techade: Chips for Viksit Bharat' program · official · published 2024-03-13 · origin pib:2014078
- Major Milestone in India's Semiconductor Journey as one of India's first end-to-end OSAT Pilot Line Facility Launched in Sanand, Gujarat · official · published 2025-08-28 · origin pib:2161666
- Prime Minister Shri Narendra Modi inaugurates the CG Semi Outsourced Semiconductor Assembly and Test (OSAT) facility in Sanand, Gujarat · official · published 2026-07-04 · origin pib:2281125
- Tata's Rs 27,000-Crore Assam Semiconductor Plant Begins Pilot Chip Production · gdelt · published 2026-10-03 · origin assam-cm-statement:2026-10-03
- Tata Electronics Begins Semiconductor Pilot In Assam Facility · gdelt · published 2026-10-05 · origin assam-cm-statement:2026-10-03
- Cabinet approves one more semiconductor unit under India Semiconductor Mission (ISM) · official · published 2024-09-02 · origin pib:2050859
- Kaynes Semicon rolls out first Made-in-India chips module, sent to US firm · gdelt · published 2025-10-16 · origin business-standard
- Prime Minister Shri Narendra Modi inaugurates the Kaynes Semicon Plant at Sanand, Gujarat · official · published 2026-03-31 · origin pib:2247278
- Cabinet approves Semicon 2.0 - Government delivers on its commitment for a long-term policy support to Semiconductors in India · official · published 2026-07-15 · origin pib:2284796
- Cabinet approves semiconductor unit in Uttar Pradesh · official · published 2025-05-14 · origin pib:2128605
- PM to participate in groundbreaking ceremony of HCL-Foxconn Joint Venture project on 21 February · official · published 2026-02-20 · origin pib:2230857
- PM Modi virtually lays foundation stone of HCL-Foxconn Joint Venture project India Chip Pvt Ltd (All India Radio) · official · published 2026-02-21 · origin newsonair
- Cabinet approves semiconductor manufacturing units in ODISHA, PUNJAB and ANDHRA PRADESH with an outlay of Rs.4600 crore · official · published 2025-08-12 · origin pib:2155456
- PM Modi lays foundation stone for Rs 2,500 cr ASIP chip facility in Vizag · gdelt · published 2026-08-01 · origin business-standard
- Modi lays stone for South's 1st ISM-approved chip unit in AP · gdelt · published 2026-08-02 · origin hans-india
- Groundbreaking of India's First Advanced 3D Semiconductor Packaging Unit in Odisha · official · published 2026-04-19 · origin pib:2253549
- Foundation laid for SiCSem's Rs 2,000-crore semiconductor unit in Bhubaneswar · gdelt · published 2025-11-01 · origin sambadenglish
- SiCSem breaks ground on India's first SiC fab · gdelt · published 2025-11-03 · origin compoundsemiconductor.net
- Cabinet approves two more semiconductor manufacturing units with cumulative investment of more than Rs. 3,900 crore · official · published 2026-05-05 · origin pib:2258119
- Semiconductor projects worth Rs 4,000 crore get Cabinet go-ahead · official · published 2026-05-05 · origin business-standard
Scheme-level trackers: ATMP/OSAT scheme · fab scheme · Semicon 2.0 · state policy comparison
For organisations
Need this for a decision your organisation is making?
- Monitor these institutions → We re-check the sources behind the claims you depend on and brief you when one materially changes.
- Commission a reviewed evidence pack → This evidence, re-checked against your own criteria and states, reviewed and delivered with a source register and an unknowns log.
- Compare with another state or scheme → Extend the matrix to the jurisdictions or instruments under your review.
- Submit your research question → Tell us the decision it supports and the deadline; we scope it before quoting.
We establish what is documented, what changed, who is responsible, where evidence conflicts and what remains unknown. We do not give investment, legal or policy advice — the decision stays with you or your adviser. Services · Methodology